Bob and Don, two items come to mind, that you should be aware of. First of all, on pg. 25-05, you will see 2 large corner skins ( F-1277-L and -R). If you value your sanity, you will not final rivet these 2 skins until just before you're ready to paint (I'm serious about that!). You'll have to cleco them for several trial fittings, but don't rivet them until you have to. They get in your way, big time, for all sorts of later operations in the build. Secondly, perform the entire section 28 ( fuselage tunnel fuel system), prior to installing the fuselage sides. You will thank me for this one.. There is nothing in the LSA rules that says you can't do some of this stuff in a different order. VANS plans are generally wonderful, but some of the steps can be performed more easily, in a different order. Good luck with your builds. Steve Wyman, #0038 (flying)