I’m getting ready to order the emp and was planning to order the QB fuse and QB wings at the same time, but QB fuse and wings are at least seven month lead times now. I’m thinking of ordering a SB fuselage and QB wings along with the emp figuring the lead times should allow me to build the emp and roll right into the fuselage then wings should arrive. Is this a reasonable strategy? Are there any gotchas with this approach?